Fountain Creek stabilization underway near road threatened by erosion

0
Fountain Creek stabilization underway near road threatened by erosion

South of Colorado Springs, Fountain Creek has carved deeply into the sandy soil, resulting in a towering cliff around 50 feet high. This instability has led to the closure of a nearby road since 2020. In November, the Fountain Creek Watershed District launched a stabilization project for the eastern bank, just east of Camping World and north of the Mesa Ridge Parkway exit along Interstate 25. The eroded vertical wall poses a threat to Southmoor Drive, according to Executive Director Allison Schuch.

Initially, crews are concentrating on the western bank, clearing trees and vegetation. This preparatory work will allow the river to shift westward, thus enabling repairs on the problematic eastern side. The project will incorporate large, salvaged trees from a burn area to fortify the bank.

Schuch anticipates the project will continue through the spring of the following year, curbing the significant erosion the area has experienced. This effort aims to aid downstream water users, including farmers in the Arkansas Valley. “We play a crucial role in safeguarding our creeks and communities to ensure clean water, safer communities, and resilient ecosystems,” Schuch stated.

This project marks the district’s first high-visibility undertaking, though they have completed 13 other projects along Fountain Creek, preventing 150,000 tons of material from eroding into the creek.

The district is primarily funded by $50 million from Colorado Springs Utilities. This funding was mandated by Pueblo County as part of the permit for the Southern Delivery System, a pipeline delivering water from Pueblo Reservoir to Colorado Springs. Pueblo County required Utilities to address potential issues, such as erosion and habitat loss, from increased water flow in Fountain Creek. This funding is designated for the main stem of Fountain Creek in the watershed’s southern region.

The current project is a partnership, receiving $600,000 from the city of Fountain, $700,000 in grant funds from the Colorado Water Conservation Board, and $4.9 million from the district itself. Although the site may presently appear untidy from the Fountain Creek Regional Trail, crews plan to plant cottonwoods and willows to restore the landscape. Schuch recommends healthy, low-lying vegetation to absorb floods and suggests this strategy to other property owners facing similar issues.

A public meeting regarding the project is scheduled from 6 to 7:30 p.m. on Monday, Dec. 9, at the New Jerusalem Missionary Church, 5485 Alegre Drive in Fountain. The Fountain Creek Nature Center also features a public display about the ongoing work.