COLORADO SPRINGS, Colo. (Coloradospringspulse) — Significant progress has been marked in the North Powers Boulevard extension towards Interstate 25 with the full opening of the Voyager Parkway bridge.
This week, officials announced the opening of all four lanes on the bridge. Previously, it had operated with only two lanes following a delayed partial reopening in mid-November.
“We’re about 99% complete,” stated Tim Mitros, manager of the Copper Ridge Metro District, which is initially financing the project. “The main task left is reseeding the vegetation. We’ll have a final meeting with the city and CDOT to conduct an inspection, but any pending issues will be addressed soon.”
The new bridge stands above the anticipated Powers extension, which will approach from the east. Existing ramps currently connect to I-25 between the ends of Spectrum Loop, which was the primary detour during the bridge’s construction.
Officials likely feel relieved as this project faced multiple delays since its beginning in November 2023. Initially intended for completion by August, ahead of the Ford Amphitheater’s opening, the venue opened early, and complications with utility relocation caused setbacks. Though aimed to be ready by Halloween, weather impacts and delays in concrete and paving further postponed it.
Looking forward, Mitros outlined the next phase: designing three bridges between Powers and Voyager bridge, crossing the Flying Horse subdivision. This includes the Flying Horse Club Drive bridge, Ridgeline Drive bridge, and a bridge over Old Northgate Road. Additionally, a pedestrian-sized golf cart bridge will be part of the first package.
The Ridgeline bridge will be notably high, spanning a valley from Powers’ current endpoint. Following this phase, a sound mitigation study will be launched.
“We’re collaborating with the city and the Federal Highway Administration on sound mitigation to meet all criteria,” Mitros said. “Noise has been an issue at the amphitheater, and residents, along with us, are concerned about traffic noise over the neighborhood bridge.”
The project’s final phase includes constructing a bridge over Black Squirrel Creek and creating a new interchange at Powers/Highway 83/Interquest Parkway. The Copper Ridge Metro District is funding the project with property tax revenue from local commercial and residential areas. Previously, they financed the connection of the north end of Powers Boulevard extension to I-25, which included the Voyager and Spectrum Loop bridges.
To expedite the Voyager project, the district chose to be reimbursed through the Pikes Peak Rural Transportation Authority’s renewed penny sales tax, effective since January. Despite the progress, officials anticipate the Powers extension will not be entirely complete until at least 2030.